Lithium Americas Raises Thacker Pass Cost 31% to $3.83B

Lithium Americas has raised the price tag on the first phase of Thacker Pass, its lithium project in northern Nevada, by 31 percent to $3.83 billion. The company announced the new estimate on November 11, pointing to higher labor, tariff, and contingency costs as construction continues on what it calls America’s largest fully integrated source of domestic battery-quality lithium carbonate.

At a glance
  • New cost: $3.83 billion for Thacker Pass Phase 1, up from a prior $2.93 billion estimate, a 31 percent jump of roughly $900 million.
  • Where the money went: about $395 million from labor and union wage inflation, $250 million from engineering and contractor staffing and wage rates, $150 million in added contingency, and roughly $100 million tied to tariffs and logistics.
  • Who is covering the gap: Lithium Americas plans to contribute $650 million, with $315 million drawn from Department of Energy loan reserve accounts already credited to the project, covering a total incremental need of $995 million.
  • Where construction stands: about 1,900 workers are on site near Winnemucca, growing toward 2,200 by the end of 2026, with mechanical completion targeted for late 2027 and commercial production ramping up in 2028.
  • What it will make: 40,000 tonnes a year of battery-grade lithium carbonate once Phase 1 is fully running.

Why did the cost estimate jump 31%?

Lithium Americas broke the roughly $900 million increase into several pieces in its November 11 project update. Craft labor wage inflation and higher install rates for piping, steel, and equipment make up the largest share, reflecting regional competition for skilled trades around Winnemucca. Engineering, procurement, and construction management staffing and wage rates added another slice, as Bechtel and its contractors brought on more people at higher pay to keep pace with the schedule. Tariff exposure and logistics costs, affected by fuel prices and shipping constraints, added roughly $100 million, and the company tacked on $150 million of additional contingency against uncommitted costs. The Northern Miner reported the same breakdown, noting it is one of the larger cost revisions among US battery-metal megaprojects this year.

How is Lithium Americas funding the extra $995 million?

The company says it will contribute $650 million directly to the Thacker Pass joint venture, which it owns 62 percent alongside General Motors’ 38 percent stake. Another $315 million comes from Department of Energy loan reserve accounts that are already credited to the project, and a smaller reduction in sustaining-capital reserves covers the rest. As of September 30, Lithium Americas held about $1.3 billion in cash and restricted cash, including $359.5 million held at the joint-venture level, and the company has drawn a cumulative $1.448 billion against its DOE loan to date.

What’s the timeline for Thacker Pass now?

Mechanical completion is still targeted for late 2027, with commercial production ramping up in 2028. The company’s 2026 capital spending guidance moved up to a range of $1.7 billion to $2.0 billion for the year, from a prior $1.3 billion to $1.6 billion, reflecting the accelerated pace of work on site. Workforce numbers have grown alongside the budget: roughly 1,900 people currently work at Thacker Pass, a figure the company expects to reach about 2,200 by year end.

What this means for Nevada’s lithium story

Thacker Pass sits in Humboldt County, about 100 kilometers northwest of Winnemucca, and is the cornerstone of the only large-scale lithium supply chain under construction in the United States today. Our Nevada state report tracks the project alongside Albemarle’s Silver Peak, the only producing lithium mine in the country, and the Carlin Trend gold complex that anchors the rest of the state’s mining economy. Mining Our Future’s tour covers this corner of the state on its Nevada silver and emerging plays leg, and the lithium entry in our Strategic Metals Glossary explains why this one metal sits at the center of the battery supply chain feeding electric vehicles and grid storage alike.

What to watch

Whether the new $3.83 billion estimate holds as construction moves through 2027, how quickly the Department of Energy reserve draw and the General Motors joint-venture funding close the $995 million gap, and whether the workforce ramp toward 2,200 people keeps pace with the mechanical completion target. Those three threads will show whether Thacker Pass stays on track to become the first new large-scale US lithium source in decades.