First Gold at Archimedes: i-80 Gold Starts Production Mining at Its Second Nevada Underground Mine

Fourteen months after construction started, Archimedes is a mine. i-80 Gold Corp. (NYSE: IAUX) (TSX: IAU) announced on November 23 that it has mined its first gold and commenced production mining on schedule at its Archimedes underground project — the high-grade gold project on the company's Ruby Hill property in the Battle Mountain-Eureka gold trend in Nevada, and its second underground mine to come online after Granite Creek.

At a glance
  • The milestone: production mining has commenced on schedule, following completion of the surface and underground infrastructure needed to start, including ventilation and escape raises. Lateral development to date totals approximately 3,600 metres, ground conditions remain favourable, and the underground contractor continues to exceed planned productivity rates in the upper 426 Zone.
  • What is being mined: both oxide and sulfide (refractory) material. Beginning in mid-November, oxide material from the upper 426 Zone was placed on the existing heap leach pad on the Ruby Hill property, and the company expects to begin recovering the associated gold in the first quarter of 2027. Sulfide material is being stockpiled for the Lone Tree Plant, planned for commissioning late in 2027.
  • The capital picture: construction began in September 2025 and has progressed largely in line with the March 2025 preliminary economic assessment (PEA) — except that total project capital is now expected to be approximately $10 million higher than the PEA's $47.3 million, after a decision to expand and upgrade surface infrastructure. Additional infrastructure, including more ventilation raises, a permanent mine dry and offices, continues through 2027.
  • The 2027 mix shift: the company expects the majority of material mined in 2027 to be oxide for the heap leach pad — where the PEA had assumed most 2027 material would be sulfide, toll milled at a 58% payability factor — and says that should let it increase its heap leach production outlook. Full 2027 guidance comes early in the new year.
  • The target: once the Lone Tree Plant is commissioned, i-80 is targeting consolidated annual gold production of 150,000 to 200,000 ounces beginning in 2028 from the Archimedes and Granite Creek underground projects — a company target based on its technical studies, not production guidance.
  • The resource (December 31, 2025): Indicated — 1.8 million tonnes at 7.6 g/t gold for 436,000 ounces (plus 92,000 ounces of silver); Inferred — 4.2 million tonnes at 7.3 g/t gold for 988,000 ounces. The majority sits in the Ruby Deeps Zone below the 5,100-foot elevation.

Two processing routes, one ramp-up

Archimedes carries two kinds of mineralized material, and they take two different roads. The oxide material — concentrated in the upper 426 Zone — is amenable to heap leaching at Ruby Hill, which metallurgical test work confirmed comes at lower overall processing costs than the company's oxide mill circuit at Lone Tree. The refractory sulfide material waits: everything mined in 2027 is to be stockpiled, along with a large portion of Granite Creek's oxide and refractory output, for the Lone Tree Plant's planned fourth-quarter 2027 commissioning rather than toll milling at a third party.

Underground, the work continues alongside production. Seven drill rigs are active in the lower 426 and Ruby Deeps zones, targeting approximately 55,000 metres across 140 holes, with the campaign expected to complete in the second quarter of 2027 and feed a feasibility study planned for the second half of 2027.

The honesty box

Archimedes has no mineral reserves. The company states plainly that it has started extraction without determining mineral reserves at the property, and that all of its projects other than Granite Creek underground are exploration-stage under S-K 1300. The 150,000–200,000 ounce figure is a company goal drawn from life-of-mine schedules in preliminary studies that rest partly on Inferred resources — resources the company itself notes are too speculative geologically to be categorized as reserves — and it depends on the Lone Tree Plant commissioning on schedule. Some of the oxide material now being mined sits outside the PEA's resource estimate and has not been classified as resource or reserve; the company gives no quantity or grade for it, and its contribution depends on mining and leaching results. The roughly $57 million all-in capital figure is an expectation, not a final cost. This post reports the start of production mining and the company's stated figures exactly as released.

What to watch

The ramp-up of mining rates through 2027; first heap leach gold recovery in Q1 2027; full 2027 production guidance early in the new year; the lower 426 and Ruby Deeps drill results through Q2 2027; and the Lone Tree Plant commissioning targeted for late 2027, on which the 2028 production target depends.