Past-producing gold mine ground in the Nevada high desert at golden hour, drill rig and monitoring well work in basin-and-range country
← The Pulse
Company News3 min read

Rosebud Clears Its Site-Investigation Permits: BLM Approves Blossom Gold's RBX and Rosebud West Notices in Nevada

Rosebud's next mine will be designed on data that does not exist yet — and the permits to go collect it are now in hand. Blossom Gold Inc. (TSX: BGAU) (OTCQX: BGAUF) reported on November 13 that the U.S. Bureau of Land Management has approved Notices of Intent ("NOI") for site investigation activities on the RBX claims and the Rosebud West area at its Rosebud Project in Pershing County, Nevada.

At a glance
  • Two NOIs approved: the RBX claims, southeast of the Rosebud claim block, are planned to host the project's primary infrastructure — ore conveyor, secondary and tertiary crushing, agglomeration and processing facilities, heap leach pad and waste rock storage. Rosebud West, southwest of the claims, covers the well field area where the project's water is expected to be sourced.
  • What the RBX work covers: access and condemnation holes, geotechnical test pits and shallow geotechnical probe holes over the planned facility locations — the foundation data beneath the heap leach pad, waste rock storage and processing plant.
  • What Rosebud West covers: drilling and installation of groundwater monitoring wells and test wells, against an estimated project water supply requirement of 5,000 acre-feet per annum.
  • Where the data goes: facility design and water supply planning for the Feasibility Study, the Federal Plan of Operations and the Nevada Reclamation Permit applications the company is preparing for the BLM Black Rock Field Office and the Nevada Division of Environmental Protection.
  • The rest of the program: surface drilling is ongoing, underground infill drilling is expected to commence in December, metallurgical column test results begin in December, and an updated Mineral Resource Estimate is expected at the end of Q1 2027, with feasibility initiation targeted for Q2 2027.

A permit for the unglamorous work

NOI approvals are the small end of the federal permitting ladder — they authorize investigation, not construction. But they sit on the critical path: a heap leach pad and waste rock facility cannot be engineered, and a Plan of Operations cannot be written, without foundation conditions and a groundwater baseline underneath them. CEO Rick Winters framed the approvals in exactly those terms: "Receipt of the RBX and West Rosebud NOIs allows us to maintain our critical path for expected, positive Federal and State decisions to commence construction at Rosebud in 2029."

Water is the second half of the approval. A 5,000 acre-foot-per-year supply is a material draw in the Nevada desert, and the monitoring and test wells authorized at Rosebud West are how the company proves up that supply — and establishes the baseline against which any future effects will be measured.

The ground itself

Rosebud is a past producer: the former Rosebud Mine operated from 1997 through 2000 as a Newmont–Hecla joint venture, mining underground at a cut-off grade of approximately 0.2 oz/t gold (6.8 g/t) when gold traded between US$250 and US$350 an ounce, with ore trucked roughly 120 miles to an existing Newmont oxide mill. Blossom's current vision is different in kind — evaluate the remaining higher-grade mineralization together with the surrounding larger volume of lower-grade material as a potential open pit with on-site heap-leach processing.

The honesty box

The resource on the books is inferred only: 70.755 million tons grading 0.62 g/t gold and 6.49 g/t silver, for 1.28 million ounces of gold and 13.4 million ounces of silver, pit-constrained at US$2,500 gold and US$35 silver (technical report dated December 17, 2025, effective November 1, 2025). Inferred resources carry the lowest geological confidence category — they are not reserves, and there is no certainty any of them will be upgraded or mined. The 2029 construction start, the Q1 2027 resource update and the Q2 2027 feasibility start are company targets, not completed events, and the NOI approvals authorize investigation work only — the Plan of Operations, the environmental review and the state permits all still lie ahead.

What to watch

Results from the December underground infill program and the first metallurgical column results; the updated resource estimate at the end of Q1 2027; and the filing of the Plan of Operations the RBX and Rosebud West data are being collected to support.